What can my site take? A developer's guide to feasibility studies for small housing schemes

How to find out what a small or awkward site can carry before you buy it, design it or apply for planning, and how to make the case for it to the planning authority.

Most small housing schemes are decided before anyone draws a plan. Every site, whether it's a quarter of a hectare behind a main street, a yard at the end of a terrace or a field on the edge of a town, has a number of homes it can carry without harming its neighbours, and a price at which it makes sense to build them. Finding out both early is the cheapest decision in the whole project.

Developers sometimes come to us after a site has let them down. A first scheme was refused, or an early layout promised more homes than the site could ever deliver. When we look back at what went wrong, the site was rarely tested properly before the design began.

We're an architecture practice in Smithfield, Dublin 7, and much of our housing work is on small and difficult sites of between one and thirty homes. This guide sets out how we test what a site can take, how we make the case for it to the planning authority, and what a feasibility study should give you on a scheme of around ten homes.

Start with the site

Unit numbers drive every appraisal, so it's natural that "how many?" is the first question we're asked. On a small site the answer depends on three others: what the site will allow without harming the neighbours, what the planning authority will support, and what the homes will be worth against what they'll cost to build.

The Sustainable Residential Development and Compact Settlements Guidelines (January 2024) give density ranges by the size of the settlement and by location within it, from city centres down to rural villages. The arithmetic is simple enough. A 0.2 hectare site at 50 dwellings per hectare gives ten homes, and at 40 it gives eight. On a small site, though, the range rarely decides the outcome, because overlooking, access, daylight, levels and services get there first. Two sites with the same area, zoning and density range can carry very different numbers of homes, so we look at the site before we open the spreadsheet.

What a feasibility study is

A feasibility study is a structured test of a site. It sets out what governs the site, tests two or three ways of developing it, gives an honest view of the planning risk of each and recommends a route to planning. For a small residential site we keep the report to eight to twelve pages, written for the person who has to make the decision.

It isn't a planning application, a full design, a cost plan or a valuation. Its job is to give your quantity surveyor, valuer, lender and solicitor a measured scheme to work from, so that their advice rests on something real.

Step 1: the desktop site check

Before we visit, we run a desktop check using Ireland's national open data. Within a few days it tells us most of what could stop a scheme:

  • the zoning and development plan objectives for the site;

  • the planning history of the site and its neighbours, from the national planning register;

  • protected structures, Architectural Conservation Areas, the National Inventory of Architectural Heritage and recorded monuments;

  • flood risk, from the OPW flood maps;

  • GSI geology and groundwater, EPA radon mapping and any licensed facilities nearby;

  • designated sites such as Special Areas of Conservation and Special Protection Areas, which can trigger Appropriate Assessment;

  • whether the land is on the Residential Zoned Land Tax map.

The planning history is often the most telling item on the list. Previous refusals on the site or next door, and the reasons given, are the best guide to what the council will raise again.

Water and wastewater need early attention. Uisce Éireann asks developers to make a pre-connection enquiry at the inception stage of a project, and its published average from enquiry to Confirmation of Feasibility is 16 weeks. The confirmation goes into the planning application, so on a tight programme the enquiry should go in the week the study starts.

Step 2: reading the site on the ground

Some constraints only show up on a visit. We walk the site and its boundaries, and we look at it from the neighbours' side too. We record where their windows, gardens and rooflights are, and how far away. We note the levels, the mature trees and the boundary walls, especially shared or retaining walls. We check how a fire tender, a bin lorry and a delivery van will reach the homes, how a contractor will get in and whether a crane is realistic. Rights of way and shared lanes get a note too, because they often point to a question over title.

The neighbours' windows go on the drawing first. On a backland or infill site they usually fix the plan before density does. The Compact Settlements Guidelines set a minimum of 16 metres between opposing windows serving habitable rooms at the rear or side, with scope to reduce it in some circumstances. Knowing exactly where those windows are tells you where the new building can go.

Step 3: testing genuinely different options

Most of the value in a scheme is made at this stage. We test two or three ways of developing the site and make sure they're genuinely different: houses against apartments, one block against two, a lift against own-door access. Three versions of the same idea tell you very little.

Each option is checked against the standards that apply to it. For houses that means the Compact Settlements Guidelines, including private open space of 20, 30, 40 and 50 square metres for one to four-bedroom homes. For apartments it means the National Planning Statement of 4th November 2026, with its minimum floor areas and its requirement that at least 25% of apartments are dual aspect. The development plan adds its own standards for car parking, bicycles, bins and public open space. Parts of the Building Regulations shape the plan from the start too, particularly Part M for access and Part B for means of escape and fire tender access.

For each option we measure the number and mix of homes, the floor area you can sell or let, the gross floor area you have to build, and the ratio between them. Net-to-gross is one of the most useful numbers in any small scheme. Every square metre of stair, lift, corridor and lobby has to be built, heated, lit, cleaned and insured, and none of it can be sold.

Three options on one plot: St Joseph Street, Limerick

For Limerick City and County Council, we're designing three social homes on a corner plot of about 116 square metres and just 5.8 metres wide. We tested three layouts before choosing one.

The first, a common stair and lift serving three stacked flats, gave over 50 square metres to circulation and a net-to-gross of about 75%. Its lift overrun also pushed the building above its neighbours. Own-door homes at street level looked efficient on paper, but the building came out 1.4 metres wider than the site. The third option, two flats and a maisonette reached by an external stair and deck at the rear, reached about 89% with no lift. It still left room on site for bins, bicycles, shared open space and the contractor's set-up.

We're taking the third option forward. On a small scheme, a gap of fourteen points on the same plot can decide whether the numbers work. There's more on this project and three others in our guide to small urban sites.

Step 4: an honest view of planning risk

Each option carries a different level of planning risk, and a developer needs to know which is which. We rate each one against policy (zoning, density, height and the development plan's standards), against precedent (what has been permitted and refused nearby, and why) and against the neighbours (overlooking, daylight and the likely objections). We also list the issues the council is bound to raise.

That list matters more than it used to. Under the Planning and Development Act 2024, which applies to new applications from 26th November 2026, a planning authority can request further information only once. Anything foreseeable has to be dealt with in the application itself, so the study names those issues alongside the surveys and reports that will answer them. We've summarised the wider changes in The new Planning Act: my summary of the key changes.

Sometimes the most valuable option is also the riskiest. We say so, along with what would reduce the risk: a pre-application consultation with the council, a lower height on one boundary, or a daylight study before the layout is fixed. Sometimes the site won't work at the asking price, and it's far better to find that out before you buy.

Telling the story of the site

A good scheme can still be refused if the planner can't see why it's right for the site. A big part of our work, and one that begins at feasibility, is writing the planning narrative: the account of the site, what governs it, the options we tested and why the scheme we're proposing is the right response to it.

We know what planners look for. They assess an application against the development plan and national guidelines, and they have to write a report that justifies their decision. We write for that reader. Our design statement walks through the constraints we found and the decisions they led to, so the reasoning is on the page and the planner doesn't have to reconstruct it. Alongside it, a compliance schedule sets each relevant standard (separation distances, open space, floor areas, dual aspect, parking, density) against what the scheme provides, with a drawing reference for each. Where the scheme departs from a standard, we say so and explain why the guidelines allow it.

This is where the feasibility work pays off a second time. The constraints plan, the options we ruled out and the reasons for the one we chose become the backbone of the planning case. A planner who can see that a site has been properly understood, and that the obvious questions have already been answered, is in a far better position to recommend a grant.

Step 5: the numbers that decide viability

We're architects, not quantity surveyors or valuers, and a feasibility study doesn't replace their advice. What it does is hand them a measured scheme with the costs that small schemes tend to miss already identified.

Abnormal costs come first: demolition, party walls, retaining walls, poor ground, attenuation tanks and sometimes an ESB substation. Then there are the statutory costs, which are development contributions, Uisce Éireann connection charges and Part V. Professional fees and surveys cost much the same on ten homes as on fifty, so they weigh more heavily on each home. VAT matters too. The rate on the sale of new apartments in a qualifying apartment block is 9% until the end of 2030, against 13.5% on houses.

Part V needs checking early. Since 31st July 2026, every new planning permission for housing carries a 20% Part V requirement, whenever the land was bought. Schemes of four or fewer houses, or housing on land of 0.1 hectares or less, can apply for an exemption certificate, so a site just over that threshold carries a very different obligation from one just under it.

For a sense of scale, the Society of Chartered Surveyors Ireland put the average cost of delivering a three-bedroom semi-detached house at between €354,000 in the north-west and €461,000 in the Greater Dublin Area in 2023. Its figure for a suburban medium-rise apartment was €541,000 in 2025. Those are total delivery costs, including land, fees, finance, VAT and margin, and they explain why one home gained or lost can decide whether a small scheme is viable.

Feasibility before you buy

The most useful time for a feasibility study is before you sign. A purchase price is usually based on an assumed number of homes, and if that number is wrong, so is the price. A pre-purchase check is lighter than a full study. It concentrates on what moves value: what the zoning and planning history support, the main constraints, a quick test of yield and the Part V position.

Landowners have another reason to move. Land on the Residential Zoned Land Tax map is taxed at 3% of its market value each year, and getting planning permission and starting work allows the tax to be deferred. A properly tested scheme is the first step towards that.

What you should have at the end

By the end of a feasibility study you should have enough to decide whether to buy, whether to proceed and which scheme to take to planning. For a small housing site that means:

  • a plan of the site's constraints and opportunities;

  • two or three options, each with a schedule of homes, floor areas and net-to-gross;

  • a planning risk rating for each option, and a recommended option;

  • the surveys you'll need, in the order you'll need them, typically a topographical survey, a tree survey, a ground investigation and, on a tight site, a daylight and sunlight study;

  • the design team the scheme will need;

  • a programme to the planning application;

  • a list of the costs your quantity surveyor should price.

What we've learned

The neighbours shape a small site more than any density figure, so we start with their windows, gardens and boundaries. The best option is often one nobody asked for at the start. That's why we test schemes that are genuinely different, and why we measure net-to-gross from the first sketch. At St Joseph Street, the same plot ranged from 75% to 89%.

A lift rarely pays its way on a handful of homes. External stairs, decks and own front doors keep the common area down, and on the Pinwheel Apartments each of the ten apartments will have its own front door and two aspects.

The slow things should start first. The Uisce Éireann enquiry, the topographical survey and the planning history search all belong in week one. And we'd rather tell a client early that a site won't work than have them find out at planning.

Frequently asked questions

How many homes can I build on my site?

It depends on the site more than its size. The Compact Settlements Guidelines set density ranges by settlement and location, so a 0.2 hectare site at 50 dwellings per hectare would carry ten homes. On a small site, though, overlooking, access, daylight and services usually set the number. A feasibility study tests the real figure.

What is a feasibility study for a housing site?

A short report that sets out what governs a site, tests two or three ways of developing it against the planning standards, rates the planning risk of each and recommends a route to planning. For a small residential site it typically runs to eight to twelve pages.

What do planners look for in a small housing scheme?

A clear reading of the site and its neighbours, compliance with the development plan and national standards that they can check quickly, and a reasoned explanation of any departure from a standard. We set this out in a design statement and a compliance schedule submitted with the application.

How long does a feasibility study take?

The desktop site check takes a few days. A full study takes a few weeks, depending on the site and the information available. Uisce Éireann's published average from pre-connection enquiry to Confirmation of Feasibility is 16 weeks, so that enquiry should start at the same time.

Should I get a feasibility study before buying a site?

Yes, if the price depends on an assumed number of homes. A lighter pre-purchase check concentrates on zoning, planning history, the main constraints, a quick yield test and the Part V position.

Is a feasibility study the same as a pre-application consultation?

No. A pre-application consultation is a meeting with the planning authority about a proposal. A feasibility study comes first and decides which proposal is worth discussing.

How much does a feasibility study cost?

It depends on the size and complexity of the site. We agree a fixed fee after an initial conversation about the site. It's the cheapest point in a project at which to find out that a site won't work.

Talk to us about your site

Most of a small scheme's value is decided in its first few weeks, while the site is being understood and the options tested. If you have a site, or you're thinking of buying one, get in touch. We'll start with a site check and an honest view of what it can take. If you're still deciding what kind of homes to build, see our guide to houses, duplexes or apartments.