How the brief, the approvals, the design stages and the statutory consents work when you commission a public building in Ireland.
A new public building takes years to plan, approve and build, and the first year shapes the rest. Most of the decisions that set the cost and the programme are made before any design starts: the brief, the budget, the procurement route and the approvals the funding body needs.
This guide is for project leads in local authorities, state bodies, education and training boards and community organisations who are commissioning a building with public money, often for the first time. It explains how the process works in Ireland as of November 2026, and what you’ll be asked to decide at each stage.
Start with the brief
Before you appoint a design team, write down what the building has to do. Who will use it, how many people, at what times, and for which services? What will it cost to run and maintain, and who will pay for that? Which rooms are essential, and which would be good to have if the budget allows?
The Capital Works Management Framework calls the agreed version the Definitive Project Brief. It is the document every later decision is tested against. We write it with the client and the people who’ll use the building, and we test it against the budget before design starts. A brief that changes after design starts is the most common reason public projects run late and over budget.
Approvals before design and before tender
Public capital projects are approved in stages. Since December 2023 the Infrastructure Guidelines have replaced the Public Spending Code. They set three approval gates before construction:
Approval Gate 1, approval in principle, after the strategic assessment and preliminary business case
Approval Gate 2, pre-tender approval, once the design, planning and procurement strategy are complete
Approval Gate 3, approval to proceed, after tender and before the construction contract is signed
Projects under €20 million have fewer approval stages. Funding bodies such as the Department of Education and Youth or the Department of Housing, Local Government and Heritage add their own stage reports and approvals on top. Find out early which approvals your project needs and how long each one takes, and build that time into the programme.
Appointing the design team
Public clients appoint design teams through public procurement, usually a competition advertised on eTenders or a mini-competition under a framework. The Capital Works Management Framework sets the standard conditions of engagement for consultants. Tenders are usually scored on quality and price together, so you can weight experience, methodology and the team against the fee.
A typical design team has an architect, a civil and structural engineer, a mechanical and electrical engineer and a quantity surveyor. The architect often leads the team. You’ll also need a Project Supervisor for the Design Process, and specialists where the building calls for them, such as a fire safety consultant, an access consultant or a conservation architect. Decide at the start who will act as Design Certifier and Assigned Certifier under the Building Control Regulations.
The design stages
The Capital Works Management Framework numbers the consultants’ stages (i) to (v). Each stage starts only when the client gives permission, and the client’s approval of one stage is the permission to start the next.
Stage (i), feasibility and preliminary report: surveys, options, the Definitive Project Brief, a feasibility cost and a project execution plan. Approval Gate 1 follows.
Stage (ii)(a), outline design: the outline sketch scheme and an outline cost plan.
Stage (ii)(b), developed design and statutory approvals: the developed scheme, a developed cost plan and the planning application or its equivalent.
Stage (ii)(c), detailed design and tender documents: drawings, specification, pricing document and a pre-tender cost check. Approval Gate 2 follows.
Stage (iii), tender: the tender, the assessment and a recommendation to award. Approval Gate 3 follows.
Stage (iv), construction.
Stage (v), handover: the safety file, operating manuals, the final account and a review of how the project went.
On a recent council project of ours, the programme allowed about a month for Stage (i), six weeks for outline design, about six months for developed design and statutory approvals, two months for detailed design and two months for tender. The client’s approvals between stages added to that.
Planning
Most public bodies apply to the council for planning permission like any other applicant. A council building its own project has used Part 8, with public consultation and a vote of the elected members. Under the Planning and Development Act 2024, which comes fully into force on 26th November 2026, Part 8 is replaced by a similar process under section 159. Our summary of the new Planning Act explains the other changes.
The new Act allows a council to ask for further information only once, so applications need to be complete when they’re lodged. Surveys, drainage design and heritage or ecology reports belong in Stage (ii)(b), not after it.
Building control and safety
Planning permission is only one approval. Before work starts, a new public building will need:
a Fire Safety Certificate, which takes up to two months
a Disability Access Certificate, lodged with the Fire Safety Certificate
a Commencement Notice, lodged with the building control authority, naming the Design Certifier, the Assigned Certifier and the builder
On completion, the Certificate of Compliance on Completion must be registered before the building can be opened or used.
As client, you also have duties under the Safety, Health and Welfare at Work (Construction) Regulations 2013. You must appoint a Project Supervisor for the Design Process at the start and a Project Supervisor for the Construction Stage before work begins, and you must be satisfied that each is competent.
TGD M (2022) also requires a Changing Places toilet in certain public buildings above set sizes. Check early whether yours is one of them, because the room is large and hard to add later.
The building contract
Public building works are let on the public works contracts. A building designed by the client’s team is usually let on PW-CF1, Building Works Designed by the Employer, with an Employer’s Representative who administers the contract on your behalf. Smaller jobs may use PW-CF5 for minor building works. The architect is often named as Employer’s Representative.
Cost control
The quantity surveyor prices the design at every stage. The last estimate you approve before tender becomes the benchmark for the project. Changes are cheap on paper and expensive on site, so the time to make them is before Stage (ii)(c) is finished. A complete, coordinated tender package attracts better prices and reduces claims during construction.
Engaging the people who’ll use it
Show the proposals early, in drawings and models people can react to. We run workshops with staff and users, and present to the wider community where the project calls for it. We record what was decided and why, so the brief stays clear when the team changes.
How long it takes
For a medium-sized public building, allow three to four years from appointing the design team to opening the doors. Design and approvals usually take 18 months to two years, and construction 12 to 24 months depending on size. The approvals between stages are the part most often left out of the programme.
Frequently asked questions
What is the Capital Works Management Framework?
The Capital Works Management Framework is the set of standard contracts, guidance and procedures that public bodies in Ireland use to procure and manage building projects. It covers the consultants’ conditions of engagement, the design stages, the approval points and the public works contracts.
What are the approval gates for a public building project?
Under the Infrastructure Guidelines there are three: approval in principle after the preliminary business case, pre-tender approval once the design and statutory approvals are complete, and approval to proceed after tender. Projects under €20 million have fewer approval stages.
What replaces Part 8 planning?
From 26th November 2026, council development is approved under section 159 of the Planning and Development Act 2024. As with Part 8, it involves public consultation and a vote of the elected members.
Which contract is used for a public building?
A building designed by the client’s design team is usually let on PW-CF1, Building Works Designed by the Employer. Minor building works may use PW-CF5.
Does a new public building need a Fire Safety Certificate?
Yes. A new public building needs a Fire Safety Certificate and a Disability Access Certificate before work starts, and a Certificate of Compliance on Completion before it opens.
How long does it take to deliver a public building?
For a medium-sized building, typically three to four years from appointing the design team to handover, including the approvals between stages.